Budapest, Baross Street Relief Drain
Microtunnelling Works

Client: Municipality of Budapest

Length: 48 m

Diameter: Ø 180

Technology: Open shield

The drain construction job was related to the Budapest Central Wastewater Treatment Plant project, and its goal is to relieve already existing main collectors. The contract was signed between Colas Alterra Zrt., Sade Kft. and the Major's Office of Budapest in the beginning of 2012. After designing and
permission processes, works began in March. The works’ completion deadline was October 2012.

Main construction data:

883 m open-ditch drain construction (Baross St. and Őr St.),
55 m drain construction with pipe jacking (Baross St.),
30 m ø 400 gas-line construction. 

Budapest, Baross Street Relief Drain Gallery

ARE YOU INTERESTED?

We are offering you the advantages of trenchless public utility construction. Please do not hesitate to contact us, and we’ll provide you with the best solutions for your civil engineering project.

+36 1 883 1440





COLAS ALTERRA THANKS HERRENKNECHT AG FOR PROVIDING ILLUSTRATIONS AND PHOTOS FOR THIS WEBSITE